建筑施工·第43卷·第6期 1087
已建地下通道结构下方小间距十字叠交穿越大直径原水管施工技术
王传富 1,2
1. 上海市基础工程集团有限公司 上海 200002;
2. 上海城市非开挖建造工程技术研究中心 上海 200002
摘要: 结合上海轨交14号线浦东大道站—源深路站区间施工实际,对盾构在既有地下通道结构下方小间距十字叠交穿越
大口径市政管线的施工工艺进行了研究。基于东西通道结构与原水管对盾构机的影响、盾构小间距推进对原水管及东西
通道二次扰动的影响,通过预隔离加固及同步盾构推进施工技术措施将小间距施工对上方穿越建(构)筑物的影响降到
最低。同时通过分阶段控制技术,对土压力、推进速度、刀盘扭矩、同步注浆等施工流程细化,形成完整的施工工艺,
使盾构平稳、安全地穿越原水管及东西通道,有效地保障了相关结构的稳定,总结的经验具有一定的参考价值。
关键词: 盾构穿越;小间距;预隔离;分阶段控制
中图分类号:
TU99 文献标志码: A 文章编号: 1004 -1001(2021)06 -1087 -04 DOI: 10.14144/j.cnki.jzsg.2021.06.040
Construction Technology of Crossing Large Diameter Existing Water Pipe
with Small Spacing Under Existing Underground Passage Structure
WANG Chuanfu 1,2
1. Shanghai Foundation Engineering Group Co., Ltd., Shanghai 200002, China;
2. Shanghai Engineering Research Center of City Trenchless Construction, Shanghai 200002, China
Abstract:
Combined with the construction practice from Pudong Avenue Station to Yuanshen Road station of Shanghai
Rail Transit Line 14, the construction technology of shield crossing large diameter municipal pipeline with small spacing
under the existing underground structure is studied. Based on the influence of the east -west passage structure and the
existing water pipe on the shield machine, and the secondary disturbance influence of the small spacing advance of the
shield machine on the existing water pipe and the east -west passage, the influence of the small spacing construction
on the upper crossing structure is minimized through the pre -isolation reinforcement and synchronous shield advance
construction technical measures. At the same time, through the phased control technology, the complete construction
process is formed by the detailed construction process of earth pressure, advancing speed, cutter head torque and
synchronous grouting. It makes the shield pass through the existing water pipe and the east -west passage smoothly and
safely, and effectively guarantees the stability of relevant structures. The experience has a certain reference value.
Keywords:
shield crossing; small spacing; pre -isolation; phased control
市政工程 MUNICIPAL ENGINEERING
管 顶 标 高 - 6 . 5 m, 距 东 西 通 道 底 部 约 2 . 6 m, 管 底 标 高
- 9.5 m ,距本区间隧道顶部净距约 3.1 m(图2)。
浦东大道
源
深
路
原水管 东西通道
区间隧道
源深路站源深路站
MJS加固
原水管原水管区间隧道
图1 原水管平面位置 图2 原水管竖向位置
考 虑 到 地 铁 盾 构 施 工
已建地下通道结构下方小间距十字叠交穿越大直径原水管施工技术(论文).pdf