某深基坑止水帷幕研究与应用
黄玲玲
(浙江省三建建设集团有限公司,杭州 310000)
[摘 要 ] 在工程建设中为实现对深基坑的围护,并保证施工的安全性,本研究开展了某深基坑止水帷
幕。在明确工程基本概况的基础上,设计深基坑止水帷幕。通过高压旋喷桩施工、三轴水泥搅拌桩施工、
钻孔灌注止水帷幕桩施工等操作后,完成对深基坑止水帷幕的施工。在施工后,对深基坑工程进行监测,
避免深基坑中土层位移、围护结构沉降产生,提高深基坑施工安全。
[关键词 ] 深基坑;帷幕;应用;止水
[中图分类号]
TU 753 [文献标志码] B [文章编号] 1001
-523X
(2023
)10
-0168
-03
RESEARCH AND APPLICATION OF A DEEP FOUNDATION PIT WATER CURTAIN Huang Ling-ling
[Abstract
]
In order to realize the protection of deep foundation pit and ensure the safety of construction, this study
carried out a water curtain for deep foundation pit. On the basis of clarifying the basic situation of the project, the water curtain
of deep foundation pit is designed. After the construction of high-pressure rotary jet pile, three-axis cement mixing pile and
borehole filling water curtain pile, the construction of deep foundation pit water curtain is completed. After the construction,
the deep foundation pit engineering should be monitored to avoid the displacement of soil layer in the deep foundation pit and
the settlement of the enclosure structure, so as to improve the construction safety of the deep foundation pit.
[Keywords]
deep foundation pit; curtain; application; water stop
在工程建设中,主体结构外部围护结构中的隔水
体系被称为止水帷幕,设置主体结构止水帷幕可有效
解决地下水渗漏问题,从而达到减少、阻挡地下水流
入基坑的目的。 目前,市场内应用较多的止水帷幕结构包括高
压旋喷桩、搅拌桩等,为发挥止水帷幕更高的效能与
价值。本研究将以杭州市某商业综合用房建设项目为
例,对深基坑的止水帷幕施工展开设计与研究。
1 工程概况
本研究的工程项目建设内容包括 A 、B 地块的群
体建筑,其中A 地块建筑由A–1号商务办公楼、A–2
号商务办公楼及A 地块裙房3部分组成;B 地块建筑由
B–1号商务办公楼、B–2号商务办公楼及B 地块裙房
3部分组成。地下室为满堂地下室,范围涵盖整个地
上建筑部分并局部扩大,地下室共 3层;人防地下室
设置在地下2、3层,平时作为车库使用。
2 深基坑止水帷幕设计
在实际设计时,首先需要止水帷幕进入隔水层的 深度、深基坑底相对隔水层板底厚度、止水帷幕入土
深度等参数。其中止水帷幕进入隔水层深度的计算公
式为:
L ≥0.2 Δh
–0.5 b
(1)
式中: L
为止水帷幕进入隔水层的深度; Δ
h
为深
基坑内外水头差值; b
为止水帷幕的宽度。深基坑底
相对隔水层板底厚度的计算公式为: D ≥Kr
wH
/r
(2)
式中: D
为深基坑底相对隔水层板底厚度; K
为
安全系数; r
w为水重度;H
为承压水水头, r
为加权平
均重度。止水帷幕入土深度的计算公式为: hd ≥ηΔh
(3)
式中: η
为止水帷幕入土深度系数; hd
为止水帷
幕入土深度。结合上述计算公式,对深基坑止水帷
幕进行设计。本工程地下室为地下3 层和A地块一夹
层(自行车库),地下建筑面积80 500 m
2(含人防面
积),基础桩基形式为
某深基坑止水帷幕研究与应用(论文).pdf