工程造价管理/2023年第4期水电工程大坝基坑经常性排水补偿探讨阙清华 李良峰(华能澜沧江水电股份有限公司,云南昆明650224)【摘要】水电工程大坝基坑经常性排水,包括了堰体及堰基的渗漏水、由于汛期基坑过流而造成的基坑积水、由于降雨而造成的基坑积水、施工过程中的废水(包括坝体混凝土施工积水、帷幕灌浆、固结灌浆及基岩排水孔施工废水、坡面汇水、其他可能进入本合同工作范围的施工废水)。经常性排水一般在招标文件均为总价承包,承包人根据发包人提供的地质条件进行分析判断并报价。但在实施过程中,若发生非承包人原因,实际基坑抽排水量与投标发生根本变化,导致有经验的承包人无法预见。文章首先分析基坑抽排水增加的原因,确定责任归属;其次从法律、法规方面分析基坑抽排水补偿的法律依据,从招标投标文件等方面分析基坑抽排水补偿的合同依据;最后提出几种基坑抽排水补偿方案,并且分析探讨各自的优缺点,提出建议。【关键词】水电工程大坝基坑排水补偿【中图分类号】TU-9【文献标识码】A【文章编号】1008-2166(2023)04-084-05【DOI】10.19730/j.cnki.1008-2166.2023-04-084DiscussiononCompensationforRegularDrainageofDamFoundationPitinHydropowerProjectQueQinghua,LiLiangfeng(HuanengLancangRiverHydropowerInc.,Kunming650224,China)【Abstract】Theregulardrainageofthedamfoundationpitofthehydropowerprojectincludestheleakagewateroftheweirbodyandtheweirfoundation,thewateraccumulatedinthefoundationpitduetotheoverflowofthefoundationpitinthefloodseason,thewateraccumulatedinthefoundationpitduetorainfall,thewastewaterintheconstructionprocess(includingthewateraccumulatedinthedamconcreteconstruction,curtaingrouting,consolidationgroutingandbedrockdrainageholeconstructionwastewater,slopecatchment,andotherconstructionwastewaterthatmayenterthescopeofworkofthiscontract).Generally,thebiddingdocumentsarealllumpsumcontracts.Thecontractorshallanalyze,judgeandquoteaccordingtothegeologicalconditionsprovidedbytheemployer.However,intheprocessofimplementation,iftheactualfoundationpitpumpinganddrainagevolumechangesfundamentallywiththebiddingduetoreasonsotherthanthecontractor,theexperiencedcontractorcannotpredict.Thispaperfirstanalyzesthereasonsfortheincreaseoffoundationpitpumpinganddrainage,anddeterminestheresponsibilityattribution;secondly,analyzethelegalbasisoffoundationpitcompensationpumpinganddrainagefromtheperspectiveoflawsandregulations,andanalyzethecontractbasisoffoundationpitpumpinganddrainagecompensationfromtheperspectiveofbiddingdocuments;finally,theauthorputsforwardseveralcompensationschemesforfoundationpitpumpinganddrainage,analyzestheiradvantagesanddisadvantages,andputsforwardtheauthor'ssuggestions.【Keywords】Hydropowerengineering;Damfoundationpit;Compensationfordrainage作者简介:阙清华(1979—)男,福建上杭人,高级经济师,主要从事水利水电工程合同管理、工程造价咨询等工作。李良峰(1977—)男,重庆开县人,高级经济师,主要从事水利水电工程合同管理等工作。收稿日期:2022年11月交流园地84
一、工程概况某 水电站 大 坝土 建及 金 属结 构安装 工程包括大坝基础处理工程、大坝土建工程、消能防冲建筑、金属结构及机电附属设备安装等工程,承包人在基坑抽排水施工 过程 中,实测 的经 常 性排 水 最大强度:开挖阶段为533.9m3/h、浇筑阶段为560m3/h。根据投
水电工程大坝基坑经常性排水补偿探讨(论文).pdf