作者简介:阙清华(1979—),男,福建上杭人,高级经济师,主要从事水利水电工程造价管理、合同管理等工作。李良峰(1977—),男,重庆开县人,高级经济师,主要从事水利水电工程合同管理等工作。收稿日期:2022年6月水利水电工程锚索超注浆补偿探讨阙清华李良峰(华能澜沧江水电股份有限公司,云南昆明650224)【摘要】在地质条件差的水利水电工程坝基、边坡、洞室边墙及顶拱等部位,为提高建筑物的抗裂能力和防裂能力,经常设置锚索,故水利水电工程锚索属于常见项目。锚索项目具有工期短、造价低、布置方面、施工干扰小、施工技术易掌握等特点。锚索施工包括造孔(钻孔、固结、扩孔)、编索(除锈、编索)、吊装(运输、吊装)、放束、张拉(张拉、安装等)、封孔灌浆等施工步骤。在封孔灌浆施工环节,因各种原因,常导致注浆量远超过投标量,产生超注浆。文章首先进行超注浆的原因分析,确定超注浆的责任归属;然后从法律、法规角度分析锚索超注浆补偿的法律依据,从招标投标文件等角度分析锚索超注浆补偿的合同依据;最后提出几种锚索超注浆补偿方案,分析探讨各方案的优缺点,并提出建议。【关键词】水利水电工程锚索超注浆补偿【中国分类号】TU-9【文献标识码】A【文章编号】1008-2166(2023)02-061-04【DOI】10.19730/j.cnki.1008-2166.2023-02-061DiscussiononoverGroutingCompensationofAnchorCableinWaterConservancyandHydropowerProjectsQue Qinghua, Li Liangfeng(Huaneng Lancang River Hydropower Inc., Kunming 650224,China)【Abstract】Inthedamfoundation,sideslope,sidewallofcavernandtoparchofwaterconservancyandhydropowerprojectswithpoorgeologicalconditions,inordertoimprovethecrackresistanceandcrackresistanceofbuildings,anchorcablesareoftenset,sotheanchorcablesofwaterconservancyandhydropowerprojectsbelongtocommonprojects.Theanchorcableprojecthasthecharacteristicsofshortconstructionperiod,lowcost,layout,smallconstructioninterferenceandeasytomasterconstructiontechnology.Theanchorcableconstructionincludestheconstructionstepsofholemaking(drilling,consolidation,holeexpansion),cableweaving(derusting,cableweaving),hoisting(transportation,hoisting),beamreleasing,tensioning(tensioning,installation,etc.),holesealinggrouting,etc.Duringtheconstructionofholesealinggrouting,duetovariousreasons,thegroutingamountisfarmorethanthebiddingamount,resultinginovergrouting.Firstly,thispaperanalyzesthecausesofovergroutinganddeterminestheresponsibilityofovergrouting.Secondly,thelegalbasisofanchorcableovergroutingcompensationisanalyzedfromtheperspectiveoflawsandregulations,andthecontractbasisofanchorcableovergroutingcompensationisanalyzedfromtheperspectiveofbiddingdocuments.Finally,theauthorputsforwardseveralcompensationschemesforovergroutingofanchorcable,analyzestheiradvantagesanddisadvantages,andputsforwardtheauthor'ssuggestions.【Keywords】Waterconservancyandhydropowerproject;Anchorcable;OvergroutingcompensationEngineeringCostManagementCostManagement61
工程造价管理/2023年第2期一、工程概况某 水电站 大 坝土 建及 金 属结 构安装 工程包括大坝基础处理工程、土建工程、消能防冲建筑、金属结构及机电附属设备安装等工程,承包人在进行泄水建筑物坝下0+154.0m至电站尾水出口边坡锚索施工中,严格按施工规范要求以及设计要求进行操作,并通过灌浆自动记录仪记录灌浆相关数据。经过对灌浆数据
水利水电工程锚索超注浆补偿探讨(论文).pdf